How long does it take to build a pool in Canberra?
If you're thinking about installing a swimming pool in Canberra, one of the first questions you'll likely ask is: how long does it take to build a pool? While the exact timeframe can vary depending on your design, site conditions, and approvals, most residential pools take 6 to 12 weeks from excavation to completion.
In this blog, we’ll break down the process step-by-step, so you know what to expect (and how to avoid unnecessary delays!)
What impacts the timeline of a pool build in Canberra?
Several factors affect how long it takes to build a pool, including:
Your chosen pool type (concrete, fibreglass, plunge pool, etc.)
Weather and Canberra’s seasonal conditions
Council approvals and site access
Changes to your design mid-project
Availability of materials and trades
Step-by-step timeline for building a pool:
1. Design & approval phase (2–4 weeks)
Once you’ve selected a Canberra pool builder, the design process begins. During this phase:
Site is assessed
Concept plans are drawn up
Engineering and council approvals are lodged (in the ACT, this step can take 2 to 4 weeks depending on the complexity and approval process).
2. Excavation & groundworks (1 week)
Once approved, construction begins with excavation. Canberra’s soil conditions (including clay or rock) can impact this step. Typically:
Site is cleared and marked
Pool shell is excavated
Ground stabilisation and footings are installed (if required)
3. Pool shell installation (2–4 weeks)
Fibreglass pools are faster as shells are pre-made and installed within a few days.
Concrete pools take longer, requiring formwork, steel, and concrete curing.
Curing time is crucial to ensure structural integrity, especially for concrete pools.
4. Plumbing, electrical & equipment setup (1–2 weeks)
Filtration systems, lighting, and water features are installed
Plumbing and electrical components are laid out to meet safety codes
5. Tiling, interior & coping (1–3 weeks)
Tiling, plastering, or pebblecrete interior is applied
Pool coping and surrounding paving or decking is completed
6. Fencing, landscaping & final inspection (1–2 weeks)
ACT laws require compliant fencing before filling the pool
Final inspection ensures it meets safety and structural standards
Total pool build time in Canberra: 6 to 12 weeks
Some pools are completed faster, especially fibreglass installations. Custom-designed concrete pools or complex landscaping may extend timelines.
How to avoid delays in your Canberra pool project
Choose an experienced Canberra pool builder who knows local conditions
Finalise your design early to avoid mid-project changes
Ensure quick council approval with correct paperwork
Stay in close communication with your builder throughout
Thinking about building a pool in Canberra?
At ACT Pools, we manage the entire process—from design to approvals and completion—ensuring your pool project is delivered on time and on budget. We’re experts in building pools that suit Canberra’s unique climate and soil conditions.
Why ACT Pools?
Full support with council and planning
Experienced local team
Clear timelines and project updates
10+ years building pools across the ACT
Contact us today to discuss your dream pool and get a realistic timeline tailored to your property.